Project
Terrace of industrial units to create 3no. separate units
Client
Goodman
Value & Duration
£4m - 26 weeks

A new build 3 unit terrace scheme with associated service yards, car parking and access roads. Perimeter retaining walls were introduced on three sides of the site to allow the earthworks to achieve a site balance.

Due to extended steelwork procurement periods at the point of contract award, steelwork was not able to reach site unit week 14 of the project. As a result we elected to complete all drainage, external services and external finishes including external lighting and soft landscaping ahead of steel erection.

Back to top ▲