Project
New Build Industrial, Minworth
Client
Bericote / ASDA Walmart
Value & Duration
£17m - 32 weeks

This project involved construction of two new industrial units totalling 212,000ft2 on a site that had been cleared following its previous industrial use.

The larger of the two units is an automated internet shopping facility for one of the world’s major retailers. We have completed both the base build works and comprehensive fitting out works for the retailer.

Due to the long co-ordination and design phase we re-sequenced the programme to complete the external works as far as possible before the steel frame for the building arrived on site, with block paving, tarmac, concrete yards and even landscaping works completed in advance of the steelwork.

The second unit was a simple speculative unit for the local Midlands market.