Project
Warehouse unit with two storey office accommodation
Client
Dubai Ports World
Value & Duration
£8m - 24 weeks

A new build warehouse, offices and external works at the London Gateway park that is operated by Dubai Ports World. The 110,000ft2 project included measures to accommodate the addition of a freezer and chill store for the incoming occupier. The foundations and floor slab of the building were piled with precast concrete piles. The development achieved a BREEAM Excellent and EPC A.

The works, including office fit-out were completed within 24 weeks of receiving instructions from the employer. Construction of a high quality building including earthworks, piling, office fit-out and all external works whilst incorporating all of the specialist sub-contractor lead-in periods and detailed design periods is a significant achievement.