Project
Warehouse unit with two storey office accommodation, infrastructure to accommodate new logisitics park
Client
DBsymmetry
Value & Duration
£10m - 26 weeks

The first unit on a new DB Symmetry Logistics Park, our works included the warehouse, offices and associated external works for a 217,000ft2 unit. Our works also comprised infrastructure estate roads and earthworks for the wider estate. Part of our value engineered approach was to stabilise earthworks materials with lime/cement stabilisation to ensure that earthworks could continue through the winter months.

Our works were co-ordinated with a programme of archaeological excavations together with a series of new watercourses and watercourse diversions. The works were completed within a 26 week programme.