Project
Logistics Regional Hub Building for TNT
Client
Exton
Value & Duration
£12m - 35 weeks

This project involved construction of a new 133,000sqft cross dock distribution facility for TNT. Works included two storey office, gatehouse/security screening facility, integral vehicle maintenance unit and fuel island.

The site located just off Junction 1a of the M25 required extensive earthworks and vibro ground improvement works to the building footprint. Works also included over 40,000m2 of external concrete service yards.

Back to top ▲